April 12, 2021
Setting the stage

April 12, 2021
Just an hour after the official groundbreaking ceremony

April 19, 2021
Tree and asphalt removal completed.

April 27, 2021
Building footprints are materializing.

May 27, 2021
The foundation for the family shelter building is being poured.

May 27, 2021
The basement walls are added to the family shelter building’s foundation.

June 14, 2021
Final preparations are made for placing the foundation for the child care and administration building.

June 14, 2021
The foundation for the child care and administration building is completed.

June 23, 2021
Walls begin to go up on the family shelter and the first supports are in place for the child care and administration building.

June 29, 2021
Work is progressing steadily. First floor walls are all in place at the family shelter building (right).

July 14, 2021
The frame of the child care and administration building (left) takes shape, while the second floor walls are already in place on the family shelter building (right).

July 14, 2021
The roof begins to go on the family shelter building.

July 26, 2021
The roof is on and the windows are in place on the family shelter building.

July 29, 2021
The metal frame of the child care and administration building continues to grow even as the first walls go up.

August 9, 2021
The skeleton of the child care and administration building (left) is close to completion, while the family shelter building (right) appears nearly finished from a distance.

August 19, 2021
The family shelter building appears nearly finished from the outside.

August 19, 2021
Inside the family shelter building, utilities are already being installed.

September 1, 2021
Exterior walls are up around the child care and administration building and the roof is going on.

September 9, 2021
The child care and administration building will soon be fully enclosed once the final roof decking panels and exterior windows are installed.

September 9, 2021
As you can see, installation of the roof decking panels is nearly complete on the child care and administration building.

September 26, 2021
The roof decking is completely in place on the child care and administration building.

September 26, 2021
The sidewalks are being poured around the family shelter building.

October 13, 2021
The task of pouring concrete for curbs around the buildings and parking areas is nearly complete.

October 21, 2021
Most of the windows have now been installed in the child care and administration building.

October 21, 2021
At the family shelter building, all of the drywall has gone up inside.

November 4, 2021
Grass is starting to grow in the green areas around the new site!

November 4, 2021
Shrubs and other greenery have gone in around the buildings.

November 10, 2021
The big news today is we have pavement!

November 19, 2021
Workers are preparing to pour concrete for the entrance stairs and ramp outside the child care and administration building.

December 2, 2021
All of the drywall is now installed in the child care and administration building.

December 8, 2021
All of the HVAC units have been installed in the family shelter building.

December 8, 2021
Workers have begun installing the siding on the exterior of the family shelter building.

December 18, 2021
Happy holidays, everyone!

January 3, 2022
Can you believe it’s January? Exterior siding is nearly complete on the new family shelter building. Grass is starting to grow!

January 12, 2022
What will one day be the kitchen for our child care center is beginning to take shape. It just needs some flooring, cabinets, appliances, etc.

January 25, 2022
That’s more like it! Vinyl plank flooring has been installed and cabinets are going up in the child care center.

January 25, 2022
Along with all the progress being made inside, exterior siding is going up on the child care and administration building.

February 1, 2022
Future outdoor classroom and playground adjacent to our child care building.

February 1, 2022
Complete siding, windows, and doors in place on the main entrance to the child care and administration building (the side facing Morton Street). Our new sign will be added soon!

February 1, 2022
The sun sets on the nearly completed exterior of the new family shelter building.

March 5, 2022
A crew of volunteers came in on this Saturday to build all of the fences that enclose our outdoor play/learning areas at the new child care and administration building.

March 5, 2022
Our hardworking team of fence-building volunteers who helped install all of the playground fences at our new facility.

March 25, 2022
Installation of the kitchens is underway in our family suites. This space will soon be filled with dual stove/oven ranges for 2 families.

March 25, 2022
Fresh sod has gone in at the outdoor play/learning spaces for our early childhood and pre-K classrooms.

April 7, 2022
The sign has gone up on our new child care and administration building!

April 7, 2022
Opening soon!

April 19, 2022
The lights are on inside our new child care and administration building. We’re almost ready to move into our new facility.

April 19, 2022
It’s a peaceful night outside our new family shelter building. Work continues inside to make the space move-in ready.